AEROSPACE INDUSTRY
UPDATE
August 2015
McIlvaine Company
TABLE OF
CONTENTS
Arlon
Upgrades Cleanrooms at its Californian Facility
Space
Station Processing Facility Update
Arlon Electronic Materials (a division of Rogers Corporation),
a US manufacturer of specialty high performance materials used in the defense,
space and avionics industries, has made significant capital investment in
upgrading cleanroom facilities at its site in Rancho Cucamonga, CA, US.
The company has installed new equipment in its build-up and
sheeting processes to reduce foreign object debris (FOD) and enhance cleanliness
of the manufacturing process of all of its prepreg and laminate materials. Arlon
said it is moving forward with plans to expand the use of cleanroom technology
into other processes throughout its operation for the rest of this year and
next. Key improvements include enclosing prepreg sheeting and build-up areas
using modular technology, resulting in dramatically smaller spaces to keep free
of particle contaminants.
The overall footprint of the build-up area has been reduced by
more than 50%, enhancing environmental control and particle reduction. The
improved cleanrooms with substantially reduced particle counts are rated ISO
Class 7 (Class 10,000). A new air filtration system results in 50 to 60
volumetric air exchanges every hour and creates positive pressure within the
room. This ensures the constant filtration and introduction of cleaner air,
which aids in the removal of any residual particulates. Particle count data
indicates a 70% reduction in airborne particles during the build-up process
since the installation of the various cleanroom technologies. The company has
always used HEPA-filtered air and daily room cleaning protocols to keep
particulates to a minimum. The implementation of new cleanroom equipment and
controlled air flow has allowed operational cleanliness to reach a higher
standard.
One of the most recent research labs was built as part of the
Space Station Processing Facility (SSPF) at Kennedy Space Center (KSC) in 2014.
This science lab was built to conduct experiments on various species to
understand their performance both on Earth and in Space under different
environmental conditions.
Despite many constraints, they plan to demonstrate how a
highly energy efficient facility achieved LEED Silver certification. The
challenges of this project are due to some of the following requirements:
The project site was located on a previously
developed land.
The site location limited the building
footprint by the adjacent access roads and other existing
buildings.
New facility had to be located adjacent to one
of the most secure facilities with high value payloads and
national assets.
Utilities had to be brought from adjacent
facilities whose operation could not be disturbed.
Limited time
for construction due to proposed launch schedules
stringent facility environmental requirements (for example,
shall maintain 40 to 65% humidity controllable in 1%
increments).
Facility should be LEED certified with energy efficient systems.
Design-build process shall meet the limited budget.
All products had to comply with Buy American Act.
Control system needed to be highly flexible and had to control
the fully redundant mechanical systems.
Control system needed to interact with central control system
for the entire KSC.
The facilities and operation had to be AAALAC certified.
Background
Building a standalone vivarium which maintains pressure relationships between
various communicating spaces and that maintains positive pressure with respect
to exterior environment is a huge challenge. The exterior walls had to be
designed as breathable and as well as cleanable for the level of cleanliness
required in a hot and humid climate. The following wall detail was used to build
the lab envelope so that above goals could be achieved. Exterior water proofing
had water vapor permeance less than 1 perm and interior water based epoxy
coating had approximately 5 perms.
Typically, there are options for orienting a
building and the selecting the most optimum building orientation for the least
amount of energy use. However, this site was selected based on adjacency,
security, and available utility constraints. Therefore, developing a building
footprint and floor plan that meets the functional requirements of a demanding
lab with all the functionalities included was a huge challenge. Several design
meetings were conducted to finalize, select the most optimum acceptable layout
by the users and facility maintenance personnel and to meet life safety
regulations.
Besides the normal structural goals for ordinary structure, there were
additional challenges for this facility. To provide the optimum facility within
budget and schedule, both engineers and architects held several meetings with
the various construction trades to select the most durable and available
construction materials for the new Science Annex. The following paragraphs
summarize some of the challenges and how they were overcome.
To be sustainable and green, this project opted to
use materials that have high recycling contents such as concrete masonry units
(CMU), concrete with slag and fly ash, structural steel, steel joists, and steel
deck. The use of these materials helped capture some LEED points.
To control humidity precisely, chilled water option
was selected for this small building by the mechanical design team. Routing
chilled water supply and return from the adjacent SSPF mechanical room
(approximately 200 ft. away with 80 ft. in change in elevation) to the Science
Annex was challenging. The selected option was to route the pipes up to the SSPF
roof, continue to run the pipes on supports over the SSPF High Bay (contains
space station modules and other flight hardware), and then run the pipes down
along the side of the 80 ft. high building to the AHUs located on the ground
adjacent to the Science Annex. The challenge was to maintain water tight roof
over the expensive flight hardware for a roof that is 20 years old. Then, select
suitable structural members to support the curbs that carry the chilled water
pipes. The pipe roof penetration curb and gooseneck was custom designed. The
pipe supports were designed using finite element model to determine precisely
the pipe deflections and reactions on the roof structure.
To meet the stringent wind pressures on the walls
and roof of the Science Annex, reinforced CMU load bearing walls and steel deck
for the roof were selected. Steel deck was modeled structurally as diaphragm
system to resist lateral wind loads.
Since the facility footprint was very limited, it
became clear as the design developed that more space was required to house
mechanical equipment. To meet this demand, a mezzanine within the mechanical
room was added during the design-build process. The design was challenging as
the vertical clear space in the mechanical room was already established. Shallow
roof framing members were utilized to maximize the head room above the
mezzanine.
To meet the budget, only 8-in CMU block could be
used for the exterior walls. To keep the 8-in CMU and deal with the 157 MPH wind
speeds at the site location, and wall heights, the design engineers integrated
the wall into the floor slab. This created a two span condition versus one
simple span. By doing so, the use of reinforced 8-in CMU was made possible.
Mechanical Systems Challenges
The prime goals of this facility design included:
Maintain required air changes (15 ACH at minimum for several
spaces) and adjust as needed based on facility occupancy
Maintain positive and negative pressures in various
interconnected spaces at all times based on the type of space
use
Design a couple of spaces with both +ve and –ve pressure option
with respect to corridors with switching capabilities through
control system when needed
Maintain space temperature from 65 to 78 F (adjustable in 0.5 F
interval)
Maintain RH in critical rooms from 40 to 60% adjustable in one
percent increments throughout the year
Maintain overall building pressure to be positive to ensure
humidity control under all conditions
Provide highly energy-efficient systems meeting the above goals
using once through air conditioning system.
To meet the above challenges, a variable speed direct expansion (DX) type AC
system was initially selected. However, through the energy analysis exercise it
was realized that getting enough LEED credits and control of precise humidity
would be very difficult with this approach even though it is possible.
Therefore, we explored options to bring chilled water from a central
water-cooled chiller plant located approximately 1,200 ft. away from the
building. We had to incorporate a circulation pump to the existing primary/
secondary loop to achieve this. This option was achieved with no additional
costs to the customer.
The air-handling unit was designed as a once through system to maintain the
highest level of cleanliness specified. Filtration was achieved with UV lights
and HEPA filters. All the mechanical and control systems were designed with 100%
redundancy. Due to the fact that animals are very sensitive to the rate of
change in temperature, we included electric heat for the terminal heats with SCR
control instead of steam heat even though enough steam was available in the
facility. Steam heat is more effective and would change the room temperature at
a much faster rate than desired.
The steam boilers were designed to handle both autoclave and cage washer steam
loads with condensate recovery without any pumps. Natural gas service was
extended to this facility for steam boiler and water heaters. Water heaters were
designed for 180 F high temperature hot water supply to minimize the steam use
in cage washer and maximize energy savings.
The humidifier system uses RO/DI water so that cleanliness can be maintained. In
addition, the DI water is used for animals’ consumption. Packaged DI water
system was selected with a 500 gallon storage tank. Compressed air was extended
from adjacent main building using one of the branch connections available and
adding another isolation valve for future without disturbing existing
operations.
The entire control system sequence of operations and failure analysis was
developed based on different operating scenarios at this lab and possible
impacts due to either equipment or a control device failure. Alternate means of
control without losing temperature, humidity, and pressure relationships were
identified. Switch over of major equipment was tested to ensure that facility
conditions can be restored within three minutes in case of a major equipment
failure such as an air handler or exhaust fan.
The project required receptacles every 4 ft. in each of the rooms. The required
number of circuits created extensive conduit planning to coordinate with other
disciplines. They had to relocate some of the existing feeds to other buildings
to make room for feeds to this building.
LEED Certification
The SSPF Science Annex laboratory had to be LEED silver certified per NASA
mandates for all new buildings. It was a very challenging endeavor as this is a
lab building with once through air conditioning system with prescribed air
changes per hour requirements. The lab operation is typically dictated by
mission requirements. Therefore, the available flexibility in operation (based
on whether the lab is in operation before the mission or in use aft.er the
mission) was thoroughly modeled/controls
programmed to save as much energy as possible without losing cleanliness
requirements.
Figure 2 shows the various LEED points obtained for
LEED silver certification. This building is designed with no windows for
lighting control of various experiments. The roof was insulated with R-30 and
walls were insulated with R-14 to minimize heat loads of perimeter spaces.
Supply air temperature reset was incorporated to minimize reheat. Highest
possible efficiency water heaters and steam boilers were used in this project.
Several recycled materials were used to be environmentally friendly. The
building operations were thoroughly reviewed for AAALAC certification.
Conclusion
In summary, the Science Annex design-build process
was a huge success due to extensive planning, by modeling the building systems
thoroughly and updating during construction phase, the ability to work with the
selected group of contractors who got involved right from the design phase, an
understanding the limitations from the existing utility services, extensive
knowledge of the system and support from the customer side, and the fact that a
design professional was involved from concepts to commissioning phase to make
various critical decisions.
In conclusion, the integrated design-build delivery
process is successful for highly complex projects with the right team of
engineers, architects, and contractors with customer involvement throughout the
process.
Acknowledgements:
NASA KSC Team, CDE Design and Construction Team
DJ Design Architects, Daytona, FL, Doug Wilson General Contractors, Cape
Canaveral, FL
ALC Controls, Orlando, FL, Enthalpy ENC Mechanical Contractors, Orlando, FL
Kannan Rengarajan, P.E., is one of the founders
of CDE serves as the Lead Mechanical Engineer. He holds a Masters degree in
Mechanical Engineering. He has over 32 years of multi-disciplinary
engineering projects experience and has authored several articles in the HVAC
field for hot and humid climates. www.cdeco.com
Luft.i Mized, P.E., is one of the founders of CDE serves as
the Lead Structural Engineer. He
holds a Masters degree in Structural Engineering. Mr. Mized has over 32 years of
multi-disciplinary engineering projects experience and was nominated as the
“Engineer of the Year” by Canaveral Council of Technical Societies/NSPE.
www.cdeco.com
McIlvaine Company
Northfield, IL 60093-2743
Tel:
847-784-0012; Fax:
847-784-0061
E-mail:
editor@mcilvainecompany.com
Web site:
www.mcilvainecompany.com