TABLE OF CONTENTS
Uniontown to Spend $4.4 Million for Wastewater Upgrade
A team of engineers and consultants recently unveiled a $4.4 million plan to overhaul and upgrade the Perry County, Uniontown sewer system, which has been leaking untreated wastewater since 2005.
The work will include sewer line repairs, upgrades to the wastewater treatment plant and the purchase of 40 acres to serve as a second sprayfield for treated wastewater. Construction is expected to take about 18 months to complete.
Finding the necessary money to pay for the improvements, however, will be difficult. Uniontown, in the Black Belt, has 1,600 residents and an average household income of $12,500.
A representative of Tuscaloosa-based Sentell Engineering Inc. has been working with Uniontown officials for three years on a design and overhaul of the city’s wastewater treatment system to correct problems that the Alabama Department of Environmental Management has described as "ongoing". The failures of Uniontown’s 40-year-old sewer system have been extensively documented through ADEM records for the past seven years.
The upgrades are extensive, and Uniontown officials have agreed to borrow at least $2.5 million to get the project started.
During a 2005 inspection of the sewage plant, ADEM officials discovered a sewage overflow seeping into nearby Cottonwood Creek, which feeds into Prairie Creek and then flows into the Black Warrior River near Demopolis. That spill of untreated sewage caused the waterway to be "septic for a stretch of at least five to six miles," according to the ADEM report.
Four years later, a 2009 ADEM compliance report found additional breaches in the plant’s system that allowed raw sewage to discharge into Cottonwood Creek. According to that report, officials determined that the Uniontown plant "cannot successfully treat or even hydraulically handle the flow of wastewater that it presently receives." The addition of more wastewater from new homes or businesses would worsen the problem and likely result in more leaks, the report said. That prompted ADEM to issue an administrative order asking Uniontown to make the necessary infrastructure upgrades to fix the problem within three years. However, the leaks continued. Last year, another report found that a broken pump at the sewage treatment plant allowed 300,000 gallons of sewage into Cottonwood Creek. According to that report, the problem was "ongoing."
Recently, two different sewage leaks were discovered. One involved the malfunction of a lift station that allowed raw sewage to leak once again into Cottonwood Creek. At the same time, it was discovered that too much treated wastewater was being poured into the city’s 50-acre sprayfield, where treated sewage is supposed to slowly seep into the ground. A berm around the sprayfield collapsed, leaking discolored, foul-smelling wastewater into Freetown Creek and Chilatchee Creek.
Another complication is heavy rain, which adds to the amount of wastewater on the already overburdened system. Engineers said the normal 300,000 gallons a day that washes through the system spikes to about 1.2 MGD following a heavy rainstorm. That volume causes the holding ponds to overflow and release untreated sewage into nearby streams.
The plans to repair the sewer system and the funding options were discussed at a meeting at City Hall called by Perry County Commissioner Albert Turner Jr., who is spearheading efforts to solve the sewer overflow issues. Turner said he intends to address the problems not only for Uniontown, but also for the approximately 10,600 residents of Perry County.
$18 Million for Unalaska WWTP Upgrade
The city of Unalaska will undertake a major upgrade of its municipal sewage treatment plant under a settlement of a Clean Water Act enforcement action filed against the city and the state of Alaska by the Department of Justice on behalf of the EPA.
Under the proposed settlement, Unalaska will spend at least $18 million to upgrade its treatment plant over the next three years to meet the requirements of its current National Pollution Discharge Elimination System (NPDES) permit. The city has also committed to adhere to fecal coliform limits that are 50 times more stringent than the current permit’s limits.
The Clean Water Act lawsuit, filed in June 2011, alleged that the city continually violated its NPDES permit by discharging pollutants into South Unalaska Bay in excess of discharge permit limits. According to monitoring reports that the city is required to file with EPA, Unalaska’s treatment plant had more than 5,500 violations of permit limits between October 2004 and September 2011, including discharges of harmful fecal coliform bacteria that were often more than double the permit limit.
The treatment plant upgrade will significantly reduce the level of pollution, including fecal coliform bacteria, being discharged into Unalaska Bay, which is part of the Bering Sea. The city will also pay a $340,000 penalty for past NPDES permit violations.
With a year-round population of approximately 4,400, Unalaska (commonly known as Dutch Harbor), is Alaska’s 11th largest city. Lying roughly 800 miles southwest of Anchorage in the Aleutian Island chain, Dutch Harbor serves as homeport to one of the nation’s most productive commercial fishing fleets, supporting both industrial-scale fishing and fish processing. During the height of the fishing season, Unalaska’s population more than doubles, reaching as high as 10,000.
San Jacinto Begins $112 Million WWTP Project
Construction of the San Jacinto Valley Regional Water Reclamation Facility’s tertiary treatment upgrade and Plant 2 facilities will expand the wastewater treatment capacity of the existing facility to 15.4 MGD. The project will allow the Eastern Municipal Water District to meet the state’s stringent Title 22 treatment requirements.
The general contractor is PCL Construction Services.
The project includes retrofitting the existing plant facilities, adding two new digester structures, a sludge storage structure, an additional chlorine contact structure, primary and secondary clarifiers, an aerobic basin structure, a new flocculation basin, an effluent pump station, new headworks, new boifilters, new operations and administration buildings, a main electrical building, four minor electrical buildings, and a new warehouse.
The project is scheduled for completion in November 2014.
** ** **
Pinole, Hercules Move Forward with $47 Million Wastewater Upgrade
A subcommittee that is looking at plans to upgrade the Pinole-Hercules Water Treatment Plant agreed not to spend more staff time on a private company's proposal for a new water recycling plant. The subcommittee of Pinole and Hercules city council members will make the recommendation to their respective councils for a vote.
The panel will move forward with its application for a plant upgrade to the Bay Area Regional Water Quality Control Board. An upgrade to the plant is needed to handle more volume of wastewater during periods of heavy rainfall, when the treatment facility can be overwhelmed and forced to release untreated water into San Pablo Bay.
PERC Water has been trying to convince the cities to award it a contract for engineering services for its design-build project. Under its proposal, the East Bay Municipal Utilities District would sell recycled water to ConocoPhillips for use at its Rodeo oil refinery. The two cities, the refinery, the utility district and the company would share those costs. By selling the water, the project would save ratepayers in the long run, PERC Water officials have argued.
But the two cities had already awarded an engineering contract to another company by the time PERC Water submitted its private-public partnership idea. Despite a series of presentations over months, PERC Water did not convince the committee. Among the uncertainties raised was potential complications that could arise with so many decisions and commitments depending on the involved parties.
Pinole Director of Public Works Dean Allison called it a "fatal flaw" that there is no long-term commitment from ConcooPhillips beyond three to five years to buy the recycled water. He also said that the two cities' planned $47 million upgrade includes water recycling.
** ** **
Massive Expansion of Wastewater Recycling Planned at San Diego WWTP
Early next year, San Diego will finish a landmark pilot project meant to prove that the city can safely recycle sewage by purifying it into drinking water.
A two-year city study, due to be presented to a City Council committee in May, answers that question and other big unknowns, like how much it would cost to recycle sewage, where purification facilities should be built and how much sewage could be diverted from a major treatment plant in Point Loma.
The blueprint sets a goal for San Diego to recycle 100 MGD of sewage in coming decades, saying its cost would be comparable to increasingly expensive — and volatile — imported water supplies. That would represent roughly 20 percent of the region's supply.
The report calls for a major, multi-billion-dollar expansion of San Diego's water-reuse infrastructure, with new purification facilities in Point Loma, University City and the South Bay. If adopted, San Diego would join Orange County as a major pioneer in the American Southwest's fledgling efforts to turn sewage into a drinking water source.
Today, San Diego imports billions of gallons of water annually from far-off sources, a practice that consumes massive amounts of energy and leaves the region vulnerable to supply interruptions. After traveling hundreds of miles to San Diego, the water is consumed once and flushed down the toilet before being treated and pumped into the Pacific Ocean.
Environmentalists and federal regulators have pressured San Diego to expand sewage reuse. San Diego's major sewage treatment plant, which sits on the Point Loma bluffs near Cabrillo National Monument, is outdated, today operating under a temporary waiver of federal pollution rules.
The city has balked at an upgrade because of its $1.2 billion price tag. That cost could drop to $710 million if San Diego fully implements the sewage recycling strategy.
When San Diego was granted its most recent waiver, which expires in 2015, the U.S. EPA warned the city to begin seriously weighing how it would reuse sewage. The study provides the most definitive answer yet, though whether it will be enough to satisfy the EPA remains unknown.
An EPA spokeswoman said, the agency would soon meet with city officials, local water pollution regulators and environmental groups to discuss the study and the Point Loma sewage plant's future.
"The agency believes that more efficient use of treated wastewater is critical to the future of both the San Diego area and much of the Pacific Southwest," the spokeswoman said. "EPA has seen a draft executive summary and looks forward to seeing more details about the conclusions reached by the study."
Here are four key takeaways from the report:
1. Purifying sewage would greatly improve San Diego water quality. Imported water today is salty, particularly supplies from the Colorado River. The pure water produced from reusing sewage would reduce salinity in taps across the region.
2. San Diego's purple-pipe system delivers sewage treated to be safe for irrigation but not drinking. While the report envisions a small expansion of San Diego's purple-pipe system, it concludes that a major expansion would cost between $430 million and $550 million but only yield a small amount of water. Instead, it proposes new advanced purification facilities on Harbor Drive in Point Loma and at existing sewage plants in University City and the South Bay.
3. The study outlines what to do with San Diego's sewage from now until 2035. But implementing that plan will take time, and the city has a 2015 deadline to get another federal pollution waiver for the Point Loma sewage plant. A lawsuit would be necessary to create a court-ordered timeline for upgrading the city's sewage infrastructure.
4. An influential report that could dictate the future of water and sewer rates in cities across the San Diego region for decades has not been released with any fanfare. It has been routed to a City Council subcommittee without any statement from Mayor Jerry Sanders, who until recently has opposed purifying sewage as a drinking water source.
** ** **
San Jose WWTP Needs $50 Million for Upgrade, Repairs
A sewer rate increase is necessary to pay for the ongoing operation, maintenance and repairs of the San Jose wastewater treatment plant and the collection system. The plant which began operation in 2000 treats 3,100,000 MGD of wastewater at the tertiary level. The plant meets the most stringent discharge standards.
The wastewater system budget also includes fines imposed by the California Regional Water Quality Control Board that alleged discharge violations between 2006 and 2008. The state mandated a 20-year capital improvement program, which will add an additional $2.6 million to $3.8 million annually to the budget.
Because of the settlement with the California Regional Water Quality Control Board, the city is required to complete a comprehensive master sewer improvement plan. That has been drafted into three phases. The projects will add $50 million in capital projects to the wastewater budget. The projects will improve the collection system by repairing and replacing pipes to reduce inflow and infiltration and create a new equalization basin for overflow storage that will prevent overflows. Those new pipes will be pipes with an expected lifespan of 100 years, because the technology exists to make them last longer than what is in the ground now.
Wastewater Treatment Plant Manager Dave Gromm said the planned projects will fix the problems that have been troublesome for the system. "The equalization basin will see us through. Our capacity will be huge. We'll be able to run on three tanks with two on standby. We should be in a lot better shape by year three. We're going to attack the worst areas first," he said.
The city is still investigating how much of a sewer rate increase in the subsequent years will be necessary.
"The city is utilizing a financial advisor to complete the debt financing plan and will be presenting the plan to the City Council in July. The next ten years of capital projects and the debt financing for these projects will continue to have a significant impact on future sewer rates. Staff is exploring every option to 'smooth' the impact of the capital projects on the rates but there are no options but to implement the mandated annual capital expenditures of $2.8 million to $3.8 million," Ann Ritzma, director of administrative services wrote in the staff report.
There is no operating reserve for the department. Ritzma recommended the department eventually establish a reserve of 10 percent to continue to address long term improvements and the aging infrastructure of a system exposed to a coastal environment.
** ** **
$25 Million for Redding WWTP Expansion Plan
The first phase of a $25 million wastewater plant expansion plan could begin next month if the Redding City Council awards the job to a local contractor.
The council would vote to award a $9.2 million construction contract to RTA Construction/Ray Toney Joint Venture of Redding. The work would double Stillwater treatment plant's capacity from 8 MGD to 16 MGD and serve future development in two areas.
"Our flows go up quite a bit," said Brian Crane, public works director, noting that the treatment plant is at capacity in wet and dry seasons. A faulty pump at the plant last year was responsible for a spill of chlorine-rich water into the Sacramento River. The city was fined by the state for that incident. Crane, in his report to the council, said the city would avoid future violations by increasing the plant's daily capacity.
The Stillwater plant has had little work done since its construction in 1991.
The city set aside funds in 2010-11 for the first phase, which also includes design costs, contingency for unexpected expenses, construction management and contract administration and inspection. The $13.3 million job is being funded by wastewater utility funds and low-interest loans from the State Water Resources Control Board.
Completion of the project is anticipated next year. Meanwhile, Crane and his staff would be laying the ground work for the second phase. That project includes installing five miles of pressurized main pipe that would move sewage from Stillwater to the Clear Creek treatment plant. Clear Creek can filter up to 40 MGD of wastewater. That main force project is two years away and is estimated to cost $12 million.
Crane said it would save the city money in the long run, avoiding having to haul sewage from one plant to the other.
The council plans to hire a firm next month to evaluate whether the city's fee schedule is where it should be. City staff members are reviewing proposals submitted by consultants applying for the job to recommend one to the council.
The firm would study the city's future infrastructure needs and the costs involved over the next few months. At the end of year, it would submit a first report advising city leaders to either lower or raise fees. The study would wrap up in February 2013, setting up public hearings next May. A revised schedule would be in place by July.
Otis Receives Funding for Wastewater Project
On May 14 a Rural Development Northeast Area Director, joined representatives from Otis to celebrate the awarding of a $845,000 wastewater loan and a $718,000 wastewater grant.
Rural Development funds will be used to construct a non-discharging evaporative lagoon wastewater treatment system. The existing treatment plant is a non-surface water discharging facility that has compliance issues of discharging to ground water.
The Otis Sanitation District serves the town of Otis, which has a population of 534
For more information on this project go to:
http://www.rurdev.usda.gov/co
Ridgefield WWTP Needs Upgrade, Improvements
Ridgefield’s village sewer system has problems, and it will take years and millions of dollars to get them fixed.
Armed with a report documenting that the town’s sewage treatment plant regularly exceeded flow limits in its state permit, a First Selectmen wrote the Planning and Zoning Commission recently. He outlined the sewer system’s problems and said the Water Pollution Control Authority (WPCA), which oversees the system, is in the early planning stages of a sewer plant upgrade project that could address them. "Therefore any further approvals for projects should be made with this in mind," he told the commission.
"It is unlikely the WPCA will have sufficient capacity to meet the needs of all the currently proposed projects," WPCA Chairman Max Caldwell said. "We will review each project once it is approved by the land use authority and, if technically feasible, try to accommodate the project within the existing infrastructure. "If it would make the process easier, the WPCA would be willing to review tentative projects that P&Z feels would be likely to gain land use approval and provide an advisory position regarding the availability of sewer service."
Builders, too, may get advisory opinions on sewer capacity before spending a lot of money on project plans.
"The WPCA would ask that any project anywhere in town contact us," Mr. Caldwell said, "so that sewer and collection system limitations can be reviewed prior to anyone expending resources."
"Right now in Ridgefield you’ve got a situation where your flows have been going upward the last couple of years. We’re not completely sure why," said Dennis Greci, a supervising engineer at the state Department of Energy and Environmental Protection (DEEP). "The last three to four years you’ve had a gradually increasing rate where you’re nearly 90 percent of your capacity."
The state focuses on average flows over long periods of time, according to Mr. Greci.
"The flow over the course of a day varies quite a bit. The plant is designed to handle those peaks and valleys. The plant is also designed to handle some seasonal peaks." Even so, it’s near capacity. "I believe in 2010 there were five months where average flow for six months was 90 percent of design," Mr. Greci said. "And I believe in 2011 there were ten months."
Viera Requesting Bids for WWTP Rehab
Bids are due June 25, 2012 for lift station rehabilitation.
For more information go to:
http://www.h2bid.com/procurement-notice-162607.html** ** **
Winter Haven Requesting Bids for WWTP Upgrade
Bids are due June 20, 2012 for replacement and upgrade of a lift station.
For more information go to:
http://www.h2bid.com/procurement-notice-162647.html** ** **
Bonita Springs Utilities Purchases Estero Bay WWTP
Bonita Springs Utilities (BSU) has purchased the wastewater treatment system that serves Estero’s Fountain Lakes and Marsh Landing for $25 million.
"This purchase is a win-win for everyone," said Fred Partin, BSU executive director. "Residents approached BSU after the old facility created ongoing problems and was fined repeatedly for environmental and operational violations. BSU will provide residents with improved, consistent service, and destroying the old plant will protect Halfway Creek, Estero Bay and the surrounding environment."
For nearly a decade, the system malfunctioned numerous times. For example:
Following that report, residents from both communities approached BSU about purchasing the system. BSU officials examined the system and spent several months performing upgrades. The cost of those upgrades will be built into a service charge that residents of Fountain Lakes and Marsh Landing residents will pay.
BSU will operate the communities’ existing wastewater-treatment plant for 18 to 24 months, while work is underway to tie the communities into BSU’s central sewer system. Once the tie-in is complete, the Fountain Lakes facility will be demolished.
** ** **
Orange County WWTP Has Odor Control Problem
The Orange County master sewage lift station transports waste from Pine Hills to Apopka and residents say some days the odor coming from it is overwhelming.
The Orange County Utilities Department said the county did replace an odor control system at the beginning of the year. A field manager also said the county is monitoring the odor around the lift station. He said their readings say it is within normal limits. But the field manager said that doesn’t mean that there won't be a few days during the month with a strong odor.
The Utilities Department said it is continuing to monitor the station. The county said it spends $200 a day injecting an odor eliminator into the system.
Bids to High for Mokena Wastewater Plant Expansion
The village of Mokena was ready to expand its Wastewater Treatment Plant later this year, but plans hit a snag when bids came in well over budget. After securing all the necessary permits and going out to bid on expansion plans for the facility, the Village Board decided to reject all bids for the potential facility after the low bid came in at $6.9 million.
Currently the Village has $6.1 million in escrow that is earmarked for the new facility.
Village Administrator John Downs did say that the bid process was merely an "exercise in due diligence," because recent studies by the Village showed that similar projects were coming in, on average, more than 30 percent under projected budgets. He added that Mokena was hoping bids would come in between 25- and 30-percent under estimates.
"We went out to explore the market, optimally, if they would have come back in the range we thought was possible based on what we'd seen, we might be considering authorizing the bid," Downs said. "We went out because that seemed like a possibility. If we hadn't had that kind of research, then we probably wouldn't have tried to bid it. We just tried to take advantage of what we thought was a good market."
The current facility can handle up to 2.5 MGD of wastewater, of which the village currently uses 2 MGD of capacity.
Should Mokena continue to expand at its current rate, the current WWTP can handle processing for three or four years before expansion is actually necessary, Downs said.
Bluffton Requesting Bids for WWTP Improvement Project
Bids are due June 12, 2012 for the Long Term Control Plan WWTP improvement project.
For more information go to:
http://www.news-banner.com/article/view/wastewater-treatment-plant-improvements** ** **
Huntertown Considers Building $11 Million WWTP
Huntertown officials, in response to rapid growth and substantial rate hikes from Fort Wayne City Utilities, want to build and operate their own $11.2 million wastewater treatment plant. The proposal is under review by the Indiana Department of Environmental Management.
They have also approved $60,000 for studies to see whether sewer or water rates should be increased. The studies will take about 90 days to complete. The town will pay $25,500 for the wastewater study and $34,000 for the drinking water study.
Huntertown has contracted Fort Wayne to process its waste since 1988 and pays City Utilities $952,139 for that service. That contract will expire in April.
In addition, Huntertown is in the process of constructing a new $1.8 million drinking water filtration plant, part of an overall $4.5 million project to improve the capacity and pressure of the town’s water system.
Le Mars Moves Forward on Plans for New Wastewater Plant
The city of Le Mars recently took steps toward building a new wastewater plant that would divert much of Le Mars' industrial sewage and treat it about 2 miles west of town.
The city council has approved the facility plan for the about $16.9 million plant after hearing comments from a local citizen concerned about odor. But the new plant will not be built at the same location at the old plant.
"The new portion of the plant would be built 2 miles west," said a council member. "What would happen is a large portion, not all, of the industrial waste would be separated from the balance of the waste in Le Mars at its source and ... pumped via a force main out that two miles away from the community so it could go through a stand-alone, brand new industrial treatment facility."
While improvements are planned for the existing treatment plant on the northwest edge of Le Mars, the long-term plan is not to increase the size of that plant but to use its remaining life. Ultimately the existing treatment plant would no longer function as a treatment facility.
The new plant would treat primarily wastewater from two of Le Mars' industrial plants, the Dean Foods milk plant and Wells Enterprises' south ice cream plant.
The city council has not yet approved an engineering contract with Bolton & Menk, of Ames, for the project. Negotiations are ongoing.
** ** **
Foreclosure Forces Fresh Start on Lake Canyada Sewer Work
Lake Canyada a 240 lot mobile home community in rural Davenport has gone into foreclosure, forcing the Scott County Conservation Department to start over with new management to solve a long-standing sewer issue.
"We see it as positive movement to resolve the problem," Kean said. "The mortgage company understands for the property to be marketable, there has to be a sewage treatment plan. We don’t want to indefinitely treat their waste."
Orix Capital Market filed for foreclosure March 23 and sought a receivership. Cocke Finkelstein, a large property management company based in Atlanta, GA, was appointed receiver at a hearing April 26. Residents have been notified of the situation and Orix wants to resolve the sewer issue.
The county faced upgrades to its wastewater treatment plant to get its license renewed by Iowa Department of Natural Resources if Lake Canyada were to stay on the system, Lake Canyada is responsible for 90 percent of the system’s volume.
The county’s upgrades were expected to cost $200,000 to $1.2 million and the county notified then-owner I & R Properties.
I & R Properties got an injunction to keep it connected to the county system until a solution could be reached. The two sides also reached an agreement on what steps needed to be taken to help find a solution. The injunction expired May 8.
The Lake Canyada owners were required to perform a number of tasks, including installing permanent flow meters and obtaining flow data, negotiating with Davenport on parameters and fees, making necessary sewer improvements and completing pre-designs of a pumping station and pipelines, but during recent rain storms, it was apparent that little work was done by I & R Properties to solve the mobile home park’s stormwater infiltration problem.
Cost estimates I&R Properties received on the five options for wastewater treatment for Lake Canyada ranged from $297,000 for county-only upgrades to $860,000 for a Lake Canyada-only wastewater plant. Options that involve partnering with Scott County would have had I&R paying most of the costs.
** ** **
Waterloo Ready to Start $4 Million Wastewater Project
The city of Waterloo is moving forward with a project to disinfect treated sewage it discharges into the Cedar River.
City Council members voted unanimously to approve a $4.12 million contract with Story Construction of Ames to build the ultraviolet disinfection process at the wastewater treatment plant. Story Construction was the lowest bidder for the work. All five proposals submitted April 23 came in below the $5.5 million engineering estimate.
"We have to be online and operable by June 1, 2013," said Waterloo Waste Management Services Superintendent Larry Smith.
Story Construction is expecting to start work on the disinfection system by June 11, and the project should be complete by February 2013.
Meanwhile, Smith said the city is not immediately facing another significant cost for a system to lower nitrogen levels in its sewage. That was something that had been a concern in recent years. "We're within our permit limits for nitrogen now," Smith said. "Denitrification is still there, but it's not on the front burner."
Cedar Falls is also constructing a UV disinfection system for its treatment plant upstream.
Westminster Prepares for $27 Million WWTP Upgrade
This year, the city of Westminster will begin a $27 million upgrade to its Wastewater Treatment Plant, City Administrator Marge Wolf said. The Maryland Department of the Environment will fund 65 percent of the project, leaving Westminster to pay approximately $9,450,000 for the upgrade.
There is money allotted in the FY13 budget for the engineering and design work to begin, the preliminary stage of the project this year. There is no set completion date, but the upgrade is expected to take several years.
Lenox Begins Talks to Address WWTP Upgrade
Lenox town leaders have begun to address long-term problems with a costly wastewater treatment plant upgrade required by more stringent federal environmental standards.
The Select Board is also looking at exploring shared services with Pittsfield and other nearby communities. The town manager cited a Berkshire Regional Planning Commission report advocating collaboration with Pittsfield by Lenox and other communities since all cities and towns will face the same federal mandate.
The city already is acting as a semi-regional facility by accepting wastewater from Dalton, Lanesborough and Richmond and based on preliminary discussions, the city has the capacity to handle Lenox’s existing and potential future sewage-disposal needs.
The federal mandate to reduce wastewater phosphates would cost $15 to $20 million, according to town engineers.
Allendale Requesting Bids for WWTP Odor Control Project
Bids are due June 22, 2012 for wastewater treatment plant odor control improvements Phase 2.
For more information go to:
http://www.h2bid.com/procurement-notice-162558.html** ** **
Pontiac Seeks Review of Wastewater Agreement
The Pontiac City Council has unanimously voted to request independent legal counsel to give the council "guidance and understanding" of a pending contract that will restructure the city’s wastewater treatment facility.
In a deal made with Oakland County, the county will issue $55 million in bonds for the city, and the city’s wastewater treatment plant will become a public corporation. A three-person board, made up of Oakland County Board of Commissioners chairman Michael Gingell; the commission’s finance chair, Thomas Middleton; and water resources commissioner, John McCulloch will oversee the facility.
The public corporation is formally known as the City of Pontiac Wastewater Treatment Facility Drainage District.
$4.2 Million for East Bethel Force Main Project
The condition of the drying beds at the Castle Towers Wastewater Treatment Plant in northern East Bethel means the city must make about $2,000 of repairs to satisfy the Minnesota Pollution Control Agency until the facility is decommissioned in fall 2013.
According to an April 4 letter from the Minnesota Pollution Control Agency (MPCA), East Bethel did not properly maintain the solids drying bed within the existing Castle Towers wastewater treatment system.
Concentrated solids that settle at the bottom of the wastewater treatment tank within an enclosed facility are discharged to the outdoor drying beds. The solids are removed from the drying beds and stored in an outside bunker until they are eventually disposed of offsite. City Administrator Jack Davis said portions of the bed walls and liners need to be replaced or repaired.
The MPCA wrote that the first drying bed "provides a direct route for solids or runoff from rain on the solids to contaminate the groundwater of the state through the break in the drying bed walls."
According to the MPCA, the other drying beds liners conditions are unknown, but the inspection found the beds to be in a state of disrepair. The MPCA letter states that there is a potential in all the drying beds that roots from small trees could damage the liners, which could then impact the groundwater.
On March 21 he council approved the decommissioning of the Castle Towers wastewater treatment plant when presented with projected costs for keeping this facility functioning. City staff estimated that about $1.6 million of repairs would have been needed in 2013, which included $65,000 to reconstruct the drying beds.
Past 2013, City Engineer Craig Jochum estimated about $260,000 of repairs sometime in the next five years and a couple of other projects beyond 2030 that would add another $150,000 to the upkeep bill.
Instead of keeping this 38-year-old plant running, the council chose to close it. The residents in the Castle Towers mobile home park and the Whispering Aspen housing development will instead be serviced by the joint city and Metropolitan Council sewer project. A second forcemain will transport effluent from this area to the new Metropolitan Council wastewater treatment plant facility.
The forcemain project is estimated to cost about $4.2 million and will be first covered by the bond proceeds. The council will further discuss funding options this spring.
Liberty Wastewater Plans Moving Forward
The town of Liberty has taken another step forward by awarding a $177,620 contract to HDR Engineering Inc. to build a wastewater treatment plant
The company was also hired last year to conduct a feasibility study as recommended by a citizens’ task force. Utilities Director Charlie Stevens said the new contract with HDR was for engineering and related services for conducting a facility plan and anti-degradation review to determine if the city could get permitted by the Department of Natural Resources, fund, construct and operate and maintain its own treatment plant. The plan could take two to nine months to complete.
Liberty currently pays Kansas City nearly $4 million a year to treat its wastewater. Facing continuing double-digit annual rate increases for the foreseeable future, local officials have been exploring the feasibility of building a wastewater treatment facility at an estimated cost of $60 million to $75 million.
"Kansas City is under a federal mandate to fix the mess they have down there, and they’re passing the costs onto us," said a Councilman. "Our sewer bills could double every five years." The average sewer bill is about $40 a month.
There is a possibility that the city could put a bond issue on the ballot in November for the wastewater plant, but that is not a certainty.
** ** **
$66 Million for New Cape Girardeau WWTP
Construction of a new $66 million wastewater treatment plant is likely to begin sometime in August, now that the Cape Girardeau City Council has authorized a $31 million loan from the Missouri Department of Natural Resources. The city was also approved this month for a second State Revolving Fund low-interest loan to complete the job for an additional $39 million.
Bid advertisements began May 20 and they will be opened July 3, though the winning bid must come from one of 12 applicants who were prequalified.
City officials described the agreement as the first step of getting the sewer plant built, which would bring the city into compliance with state and federal standards that no longer allow untreated wastewater to be bypassed into the Mississippi River, which happens at the city's existing plant about 30 to 40 times a year.
"It's the first half of the funding that makes the whole thing happen," said Public Works director Tim Gramling. He also said that with a struggling economy, he's hopeful an upside could be that contractors are hungry for such a high-dollar project and the bids may come in under the estimated cost.
A prebid conference for applying contractors will be held in June.
The wastewater treatment plant is the biggest capital improvements project in the city's history. The plant, which will be built at the Public Works Department site will replace the current 52-year-old plant.
** ** **
St. Joseph Sewer Plant Project Grows
City staff and a host of outside engineers recently updated the St. Joseph City Council on the estimated $26 million wastewater plant project.
The project will use ultraviolet light to disinfect St. Joseph’s wastewater as part of an effort to meet requirements from the EPA, designed to keep pollutants out of waterways like the Missouri River.
"As the council knows, we have a variety of environmental issues over the next several decades. But the next several years are especially challenging," Assistant Public Works Director Andy Clements said.
A representative from Black & Veatch explained the steps the firm took to keep costs down on the project. The city originally budgeted $34 million for the job, which Black & Veatch believes can be completed for $26 million.
For example, the disinfection facility will have an original capacity of 54 MGDy, but was engineered with an expansion to 108 MGD in mind; the higher capacity will become a necessity with the addition of a high-volume treatment facility several years in the future.
Although current technology would require six channels lined with ultraviolet lights to treat 108 MGD, Black & Veatch recommended building just three now. Ultraviolet technology likely will improve in the years before the city needs the extra capacity, which could let the city treat the additional sewage with better lights, instead of building three more channels.
The project comes as a response to a mandate from the Missouri Department of Natural Resources in June 2009 that the city treat its wastewater before discharging it into the Missouri River.
As a side benefit, the disinfection project could save the city money during floods or whenever the Missouri River flows at high levels. The city currently must rent and buy diesel fuel for temporary pumps to discharge treated wastewater when the river rises above a certain point, as high water renders the gravity-flow system ineffective. The disinfection project will include a new pump station to send wastewater over the protective levee to the river.
The city previously acquired roughly 6½ acres for the expansion. Once a construction date is set, work is expected to last 18 months.
** ** **
Pleasant Hope Adding Disinfection System to Wastewater Treatment Plant
The city of Pleasant Hope is in the bidding stage of a project to construct a disinfection system at the end of the wastewater treatment beds, a project that is estimated to cost about $100,000.
For more information go to:
http://www.cityofpleasanthope.com/water-wastewater.html** ** **
$500,000 for Ozark WWTP Project
On May 7, the Ozark Board of Aldermen awarded a $573,550 contract to Smith and Edwards Construction Inc., for a wastewater treatment facility sludge aeration system improvement project. The bid includes the substantial cost of a SCADA system.
The city of Ozark operates two wastewater treatment facilities. The North 22nd Street facility has a design capacity of 2.1 MGD and the new Elk Valley facility, completed in 2009, is capable of treating 1.0 MGD. Both facilities are extended aeration ditches with biological nutrient removal, tertiary filtration and ultraviolet disinfection.
Seneca County WWTP Project Approved
Seneca County Commissioners have approved two contracts for construction of the Bascom sewer system to allow the contractor to move ahead with the more than $3.5 million project.
The action was necessary to avoid delays in construction of the Hopewell-Loudon school, which will be tied into the new system
Helms and Sons Excavating of Findlay, will do the Bascom project which includes installation of distribution and collection pipes; and construction of the wastewater treatment plant.
** ** **
Marietta Begins Phase II of$20 Million WWTP Upgrade
Marietta City Council has authorized advertisement for bids on the Glendale Road and Brentwood Street waterline replacement project and approved a multi-million loan application for the wastewater treatment plant.
That project is expected to cost more than $690,000.
In addition, council authorized application for an Ohio EPA loan totaling more than $7.3 million for the second phase of the city's wastewater treatment plant upgrade. Total cost for the upgrade, expected to be completed in 2015, is more than $20 million.
** ** **
Hudson Considering Building its Own WWTP
The city of Hudson is exploring the cost of building its own sewer treatment plant because of the rising costs of having the Northeast Ohio Regional Sewer District (NEORSD) treating its wastewater.
Hudson City Council members have asked for a report on the savings and costs of a city-owned treatment plant compared to the city's involvement in the regional sewer district.
The city will explore the potential return on the investment and rates for city customers as the next step, said city engineer Thom Sheridan.
A recent study was driven by the NEORSD increasing rates by 66 percent over a five-year period. Hudson paid approximately $1.8 million for wastewater treatment in 2011 and will pay nearly $3 million in 2017.
During the last three years, Hudson pumped approximately 1.1 MGD of wastewater to NEORSD for treatment.
The city has several other options including staying with the current system, building a new plant at the old plant's location, and discharging into Brandywine Creek, or pay for improvements to another existing plant to handle more sewage.
A new plant in Hudson would costs $38 million, with annual operating costs of $5.3 million.
In order to build a new plant, the next step for the city would be to pay $30,000 for a stream assessment and another $30,000 for stream modeling to determine if Brandywine Creek has the capacity to accept treated water while maintaining quality requirements. But council members were not ready to invest the $60,000.
Council asked Sheridan to provide a report on the potential return on an investment in a sewer treatment plant before the city finishes the budget for 2013.
Norman Considering 2 Wastewater Treatment Plant Projects
For more than a decade, Norman city leaders have been debating wastewater treatment plants.
Those treatment plants are essential to treating Norman’s growing wastewater needs. Now, an upcoming city of Norman budget item proposing the expansion and improvement of the south side wastewater treatment plant in 2013 has brought the matter to a head.
The Norman Developers Council wants the north side treatment plant — approved by voters — included in the upcoming FY 2013 budget. To that end, the developers group is asking Norman City Council to move forward in building a north side treatment plant.
Building a north side plant would increase capacity in the north and expand the service area, allowing for properties in that area to be developed, but the city must make improvements at the city’s existing south side plant in order to meet Oklahoma Department of Environmental Quality requirements.
The south side plant also will be expanded to increase its capacity. Just under $53 million is included in the FY 2013 city budget for the south side improvements and expansion.
The $53 million price for the south side plant is much lower than the cost of building a new plant on the north side. Those estimates are $85 million. Because of the cost difference and the requirements by DEQ at the south side plant, city staff has proposed moving forward with the south side plant expansion and improvements first, and then doing the north side treatment plant later as the north continues to develop.
"It’s cheaper to do the project than to get fined by DEQ," Utilities Director Ken Komiske said. "They’re going to keep fining you until you do the project."
The north side plant was to be constructed in two phases and add 4.5 MGD of treatment capacity. The existing south side plant currently processes 12 MGD. Capacity there would be increased by 5 MGD for a total treatment capacity of 17 MGD. Eventually, the two plants together would allow for a total capacity of 21.5 MGD.
** ** **
Davis Accepts Bid for WWTP Project
When the Davis city council opened bids for a new wastewater treatment plant, the reality of costs did not meet expectations.
Bids for the plant were higher than the city had hoped, but the city has been able to reduce the cost. Recently, the council approved a change order for the plant with a deduction of $779,583. The reduction, along with a $500,000 grant from the Department of Environment Quality, will cut project costs below $9 million.
"When the bids came in, we were anticipating them to come in around $8 million or less," City Manager Roger Pulley said.
Walters Morgan Construction was the low bidder. Between the city, Garver Engineering, DEQ and Morgan Construction, deductions were made in the amount of nearly $800,000. Pulley said the city was also able to keep its energy grant from DEQ, which is awarded for adding components within the project which are energy efficient.
** ** **
Long Grove Applies for Permit for New WWTP
During a special meeting recently, the Long Grove city council approved an expenditure of $8,540 to the Department of Environmental Quality to review plans for the proposed wastewater treatment plant. Variances that have been made to the original plan and discussed with DEQ were reviewed during the meeting as well. The city will now wait to see if DEQ accepts the variances before moving forward.
Garver Engineering took the plans to DEQ and there is no timetable about when the city will find out if the permit is approved. Should the city gain approval for the permit, it will then begin meeting with Municipal Finance and the Oklahoma Water Resources Board to secure funding for the project. Costs for the plant are not certain.
Once the bids begin to come in, the city will be able to start determining the cost of the project. It has been forecast to fall between $10 million to $14 million.
After meeting with the finance entities, the city will be able to send out bids. Construction is scheduled to begin Oct. 1 and the city is currently four weeks ahead of schedule.
Odor Problem at Albany/Millersburg WWTP
The Albany sewage treatment plant has an odor control problem.
The odor is the apparent result of continuing problems with a system that is supposed to be handling solids in the process of treating wastewater. The system, known as "Cannibal," is supposed to turn sewage sludge into a product that can be sold for agricultural fertilizer. Because it is not working as intended, the city instead has had to dispose of the sludge at the Coffin Butte landfill in northern Benton County.
In case the problem can’t be fixed, Public Works Director Mark Shepard said, he has budgeted $500,000 for sludge disposal costs next year, but he said it would not have an immediate effect on higher sewer rates.
Shepard said that after the city got two neighborhood complaints about the odor problem, it arranged with Allied Waste to double the pace at which the material is being hauled to the dump.
The problem first came to public attention last August when it showed up in the minutes of meetings by the joint committee overseeing management of the $75 million Albany-Millersburg Water Reclamation Facility, completed in 2009. But Shepard said the system still is not functioning as intended and the cities are in mediation with Siemens, of Waukesha, WI, the manufacturer. A meeting has been scheduled with a mediator in Oakland, CA, for June 13. If engineers can’t make the system work and mediation results in no settlement, Shepard said the cities may sue.
The system was not performing as guaranteed by the supplier, the joint Albany-Millersburg management committee was told last year. Last summer officials discussed the odor problem as well. It was said to be the result of dewatering the sludge in an open pile.
** ** **
A state-of-the-art technique for treating sludge from Seaside’s sewer treatment plant will not only be cheaper, it will be beneficial, says Public Works Director Neal Wallace. If the city buys a 10-year-old dryer to remove water from the sludge and create fertilizer pellets, annual operating costs would be reduced by about $106,000, Wallace said.
The council unanimously approved the purchase.
The Fenton Fenix Dryer, which would be added to the belt press the city already owns, would produce 200 tons of dried solids a year and would take only 20 large dump trucks to haul it away. The cost is estimated at $77,748 annually. The city currently presses water from the solids, creating 1,250 tons a year and requiring 63 loads to be transported to a landfill in McMinnville at a cost of $183,955.
The new process, which will continue to be regulated by the state Department of Environmental Quality, will not require some of the chemicals – including lime – that are used now to treat the mostly liquid sludge. The dryer will remove 90 percent of the water.
To buy the used dryer, the city would pay $392,000; a new dryer would cost $1.2 million, Wallace said. Shipping and installation costs would bring the total initial price tag to $550,000.
North Whitehall Approves New WWTP
The North Whitehall Township Planning Commission has recommended a conditional use of a wastewater treatment plant to be built to the Board of Supervisors.
Members of the Lehigh County Authority testified about the 200,000 gallon-a-day sewage treatment plant at great length, answering a myriad of questions. The plant is targeted to serve KidsPeace, Lehigh Carbon Community College and a future Walmart.
The Board of Supervisors will hear the recommendation at their next meeting, set for June 4th.
** ** **
Gallitzin Needs $17 Million for WWTP Project
When it rains in Gallitzin, the wastewater treatment plant operator must close valves to divert flow into local streams. Much of that flow is raw sewage, which should be treated at the facility. But excess flow through the plant would wash away microorganisms that break down waste, and restoring the operation often takes weeks, said John Clabaugh, an engineer with Stiffler McGraw of Hollidaysburg.
Federal and state environmental officials have warned the town of Gallitzin that the excess flow from the wastewater treatment plant must stop or huge fines could be imposed for failure to comply.
During heavy rains, inflow and infiltration overwhelms the 400,000-gallon capacity of the plant, which has an 80-year-old clay collection system.
Joel Romagna, also of Stiffler McGraw and engineer for the Gallitzin Sewer and Disposal Authority, told authority members and elected officials from the boroughs of Gallitzin and Tunnelhill and Gallitzin Township that the plant overload is a chronic problem.
Driving the guidelines are efforts to clean up the Chesapeake Bay, starting at local streams.
The only solution is replacing the collection system and private laterals at a cost of nearly $7.5 million and construction of a new treatment plant at a cost of $9.2 million. Total project cost is nearly $17 million.
$19 Million for Ellsworth WWTP
As Ellsworth Air Force Base celebrates its 70th anniversary, the South Dakota Ellsworth Development Authority is making headway on a major project – a new wastewater treatment plant.
The Legislature established the Ellsworth authority in 2009 under the Governor’s Office of Economic Development to help insure the base never closes because it is the largest employer in the state.
Construction on the $19 million joint wastewater treatment facility is expected to start in the fall. The authority-owned facility will serve Ellsworth and the city of Box Elder, which both need to replace existing systems to come into compliance with new regulations.
Choosing to replace their separate systems with a joint facility saves both the base and the city millions of dollars. It is likely the authority will contract out the daily operations of the plant.
Bridgeland Requesting Bids for WWTP Expansion
Bids are due June 14, 2012 for expansion of the capacity to 2.1 MGD of the Bridgeland wastewater treatment plant.
For more information go to:
http://www.civcastusa.com/projectdetails.aspx?projectid=1918** ** **
San Angelo Selects Hickory Aquifer for Water Treatment
The San Angelo City Council has chosen a Hickory Aquifer water treatment option that is projected to be more expensive in the long run than another, but which could give the city more flexibility in treatment and keep radioactive waste away from San Angelo's sewers.
The council voted unanimously in a special meeting to go with the ion exchange method to treat Hickory water.
The two major treatment options up for consideration were ion exchange and reverse osmosis. The reverse osmosis method uses pressure and a filter to get 90 percent of the water back, leaving 10 percent of the water in radioactive-concentrated wastewater, which could be diluted and sent to the sewer system and then on to fields for land use. For ion exchange, the resin used to filter the radiation particles is shipped to a facility that can handle the radioactive waste.
The water from Hickory Aquifer has an average of 35 picocuries per liter, and five picocuries per liter is the federal limit. The ion exchange treatment would bring the picocuries on average down to five, although it could reduce them further if the filter is switched out more often, a representative from Carollo Engineering said. The council has selected the firm to be the consulting engineers for the project.
The ion exchange would cost $115.7 million over 30 years, including operations and management costs, and it has the added problem of not having much competition for the kind of filters that can be used. That could mean a higher cost and that the filters might be hard to obtain.
An option of reverse osmosis treatment which also was seriously considered, had a cost of $102 million over 30 years.
The ion exchange method has a lower capital cost at more than $20 million compared with a capital cost for reverse osmosis and ion exchange combination of almost $40 million.
The Hickory Aquifer project is about $20 million under the $120 million budget. That money is required to be spent on the aquifer project, and it could be used for something such as increasing the well field capacity.
** ** **
Big Spring will Vote on $13 Million Water/Wastewater Projects
Big Spring voters will decide on Saturday, how to pay for improvements to their water and wastewater treatment plants.
This debate started last year after the Texas Commission on Environmental Quality gave the city of Big Spring several citations for their water treatment plants. None of these were serious violations but they do need to be fixed.
"We are needing to do some upgrades on the plants, not only to address the violations but also aging infrastructure," Assistant City Manager, Todd Darden, said.
It will cost around $13 million to fix these plants and City Council voted on an option for residents to choose how they will renovate the plants. Voters will decide if they want the projects.
$353 Million for Pierce County WWTP Expansion
Major construction on a $353 million expansion of Pierce County’s sewage treatment facility will begin late this year.
The Pierce County Council is expected to move forward next month by giving initial approval for the sale of $210 million in bonds for the project. The county plans to finish the work by mid-2016, when the current plant will be at or near capacity.
The Chambers Creek Regional Wastewater Treatment Plant will be expanded to increase capacity and meet anticipated stricter treatment regulations. Capacity at the plant, built in 1984, will increase from 28 MGD to 43 MGD, said Tim Ramsaur, the county’s wastewater utility manager. That’s enough to meet the county’s demands until 2030, he said.
The plant provides sewer service to an estimated 252,000 people in unincorporated Pierce County and in cities served by the county. Besides unincorporated areas, the sewer utility services Lakewood, University Place, DuPont, Milton and Steilacoom, as well as portions of Tacoma, Fife and Edgewood.
The construction schedule includes a pause for what is expected to be the biggest sporting event ever held in Pierce County, the U.S. Open Golf Tournament. Work will shut down for the month of June 2015. The tournament will be held at Chambers Bay which is located next door to the plant
The contractor for the project is Mortenson Construction.
In addition to the expansion, an older part of the plant will be renovated by replacing worn-out pumps, pipes and other equipment. Besides increasing capacity, the expansion will allow the county to meet stricter state regulations that require reduced nitrogen levels in the treated liquid discharge going into Puget Sound. The county is the largest sole-source contributor of nitrogen into the Sound south of the Tacoma Narrows.
A series of bond issues through 2014 is financing the project, so far about $20 million in bonds has been issued.
** ** **
Clarkston Sewer Plant Upgrade will Modernize System
The city of Clarkston is seeking a construction loan to upgrade its wastewater treatment plant.
The facility renovations will help to clean the water in a more effective and efficient way. Public Works Director Jim Martin said the technological upgrades will be expensive but are long overdue.
The construction loan will be in the amount of approximately $2 million. That is due to a shortfall in the initial budget, which was estimated to be approximately $12 million.
The lowest approved bidder for the renovations offering was $14.5 million.
Belington Requesting Bids for WWTP Improvements
Bids are due June 27, 2012 for wastewater system improvements.
For more information go to:
http://www.h2bid.com/procurement-notice-162513.html** ** **
$25 Million for Lewisburg WWTP
Lewisburg officials are taking the first steps toward major facility and equipment upgrades at the wastewater treatment plant. The estimated cost of the needed upgrades is $25 million.
The city has already initiated the project’s design work and implemented a water rate increase last fall in anticipation of the multi-million dollar undertaking.
Construction Begins on Superior Chemical-free Wastewater Project
The city of Superior is laying the foundation for a chemical-free way to disinfect wastewater.
RJS Construction has started to build the footings for the foundation of a 38-foot by 62-foot building that will eliminate chlorine and sulfur dioxide from the wastewater treatment process as the city converts the disinfection process to ultraviolet disinfection.
The current system, which uses chlorine to disinfect treated wastewater and requires sulfur dioxide to eliminate the chlorine before the water is released into the environment, is aging and needed to be replaced, said Steve Roberts, engineering manager with the city’s Division of Environmental Services.
Roberts said when the city began planning to replace the system the goal was to find a disinfection system that would allow the city to take advantage of grant funding. Nearly $1.4 million of the $4.9 million project, which includes construction of another facility to help the treatment plant on East First Street meet regulations for balancing the pH level of the water to minimize the amount of ammonia introduced into the bay, comes from federal and state grants.
By changing the system to a UV disinfection system, the city would eliminate the use of 11 tons of chlorine in the treatment process, which can affect organic matter in the water.
The project has been in planning stages for more than two years and construction is expected to be substantially complete by mid-November.
BCR Environmental Opens Haines City Sustainable Wastewater Treatment Facility
BCR Environmental has joined state and local officials in commissioning its Neutralizer facility at the Haines City Wastewater Treatment Facility.
This sustainable plant, developed in partnership with Haines City, FL recycles organic waste to produce a natural, high-quality product for agriculture use. The system was retrofitted into the existing treatment plant and allows the city to recycle wastewater residuals while reducing operational costs, energy consumption and the overall carbon footprint of the facility.
By upgrading to the Neutralizer solution, Haines City will meet regulatory requirements for wastewater treatment, save $100,000 annually in operating costs, avoid $2.7 million in capital expenditures, reduce the amount of material disposed of in landfills and become a municipality that is leading the way in a progressive approach to wastewater treatment.
BCR’s installation at the Haines City facility is its seventh in Florida. Statewide, BCR’s technology is reducing carbon dioxide emissions by about 660 metric tons annually, which is the equivalent of what is produced by approximately 130 cars. Additionally, its systems have eliminated 16,500 metric tons of waste from landfills and removed 4,500 sludge-hauling trucks from local roads.
BCR’s technology and approach to business allows small-to-medium communities, such as Haines City, to be innovative and save money, while reducing their impact on the environment and regulatory risks.
** ** **
Biowater’s Wastewater Treatment Upgrades Lagoon
New stricter ammonia limits and cold weather nitrification are two of the many issues that hinder a lagoon based wastewater treatment system. In an area where the seasonal temperatures are low, it is impossible to nitrify in the lagoons. Biowater’s system handles both of these issues and is less expensive than other retrofit solutions - <$1 per gallon to treat wastewater.
A Biowater CMFF Complete Mix Fixed-Film system upgrade consists of a Fixed Film treatment system including sieves, blowers and biomedia. This system takes the place of a lagoon in ¼ of the space. In most cases the new system provides single digit BOD & TSS numbers to POTW discharge.
The basis of the CMFF biofilm technology is the biological growth on polyethylene pieces called media or carriers. These surfaces provide a protective surface area for the biology to grow. The biofilms can handle extremely high loading conditions without any problems with clogging or shock.
The benefits of Biowater’s CMFF Complete Mix Fixed-Film treatment plant include:
•compact
•water reuse capabilities
•flexible design – use any size tanks
•easy retrofit
•remote monitoring
•eliminates sludge return
•low capital cost.
You can track all the water chemical bids in the new database in the report at:
https://www.mcilvainecompany.com/Universal_Water_Chemical/Subscriber/uwcDB/TofC.htmHere are the titles added since the last update.
Carlsbad, CA
https://www.mcilvainecompany.com/Universal_Water_Chemical/Subscriber/uwcDB/totentry.asp?ref=2022Frederick, MD
https://www.mcilvainecompany.com/Universal_Water_Chemical/Subscriber/uwcDB/totentry.asp?ref=2023Midland, MI
https://www.mcilvainecompany.com/Universal_Water_Chemical/Subscriber/uwcDB/totentry.asp?ref=2028Milledgeville, GA
https://www.mcilvainecompany.com/Universal_Water_Chemical/Subscriber/uwcDB/totentry.asp?ref=2025Schaumburg, IL
https://www.mcilvainecompany.com/Universal_Water_Chemical/Subscriber/uwcDB/totentry.asp?ref=2027Stillwater, OK
https://www.mcilvainecompany.com/Universal_Water_Chemical/Subscriber/uwcDB/totentry.asp?ref=2026
McIlvaine Company
Northfield, IL 60093-2743
Tel: 847-784-0012; Fax: 847-784-0061
E-mail:
editor@mcilvainecompany.comWeb site:
www.mcilvainecompany.com