GAS TURBINE & RECIPROCATING ENGINE

DECISIONS UPDATE

 

December 6, 2016

 

McIlvaine Company

 

TABLE OF CONTENTS

 

Can the New Administration find the Middle Ground on Global Warming?

Mississippi Power announces Electricity Generation at Second of Two Gasifiers at Kemper County Energy Facility

ABB presents the Power of Intelligent Use of Plant Data at POWER-GEN Asia

Ultrapure Water Discussion Group Updates in LinkedIn

CCR and ELG Discussion Group Updates in LinkedIn

Inlet Air Filtration

Participate in the LinkedIn Discussion Groups

 

 

 

Can the New Administration find the Middle Ground on Global Warming?

 

It is not clear presently whether the new administration will go to the extremes relative to global warming initiatives which were promised during the campaign or take a less aggressive stand. The argument has been framed about whether man causes global warming. It is unlikely that there will be any resolution of this argument between two very polarized groups. On the other hand, there is an approach which can at the very least shed light on the options and possibly result in some agreement.

 

The approach starts with the fact that a large number of voters are more concerned with “making America great again” in the near future than are worried about the welfare of citizens of the planet 40 years from now. This position varies from many who voted for Clinton. There is a difference in moral principles which needs to recognized and addressed openly. There can be resolution if both sides attest to the verity of the following statements:

 

 

If agreement can be reached on these statements, then there can be a process to resolution. Those wishing to make America great again in the short term will apply tribal values to the disproportionate impact. They will apply a present discount to future harm which is less than many who are focused on the future of the planet. One can argue the ethics but not the fact that the voter is the ultimate decision maker. Therefore, some middle ground policy can be adopted if this approach is taken.

 

Mississippi Power announces Electricity Generation at Second of Two Gasifiers at Kemper County Energy Facility

 

On November 23, Mississippi Power announced it had achieved another major milestone with electricity generated in the second gasifier at the Kemper County energy facility by synthesis gas, or syngas, from lignite. Last month, the company announced electricity had been generated in the first of the facility's two gasifiers.

 

The company announced earlier this month it was completing maintenance on the first gasifier at the plant, which followed six weeks of successful syngas production including generation of the plant's first electricity using syngas.

 

The remaining major milestones for the IGCC include successful carbon capture and integration of all systems necessary for both combustion turbines to simultaneously generate electricity with syngas. The expected date for the plant to be placed in service is Dec. 31.

 

ABB presents the Power of Intelligent Use of Plant Data at POWER-GEN Asia

 

There were lots of papers and exhibits at Powergen Asia on power plant automation. ABB’s Power Generation unit demonstrated how the intelligent use of data now available in power plants can not only deliver a competitive edge, but provide a solution to current and future challenges in the power industry.

 

They also shared innovative strategies that show plant owners how to lower risks in their projects, reduce costs and throughput times, and improve asset performance and profitability by the careful collection and analysis of plant and engineering data.

 

“We believe the success of our power generation customers will be more and more supported by the intelligent use of data generated by ever increasing connectivity of devices. The integration of those data with people expertise and knowledge will create additional services (IoTSP) in a cycle delivering unprecedented knowledge of the behavior and potential of their assets,” said Marco Sanguineti, Head of Technology for ABB’s Power Generation business unit. “The ability of ABB’s Symphony® Plus distributed control system to add customer value by utilizing the data in their systems is the result of our careful analysis of the evolving power generation market, and our customers’ changing needs driven by global mega trends.”

 

“Asia is a region with many different players in the power generation market,” said Manjay Khazanchi, Head of the Asia Pacific hub of ABB’s Power Generation business unit. “A huge transformation in energy demand is taking place globally, and the focus is now on Asia.”

 

Over the next two decades, Asia accounts for three-quarter of projected global energy demand, driven by rapid industrialization, population growth and urbanization. “While the world is moving away from coal, Asia’s dependence on it is becoming inevitable,” Mr. Khazanchi said. “Even so, the deployment of clean coal technology will represent more than half of total installed capacity, ensuring higher efficiency and lower emissions from coal generation.”

 

Repowering, modernizing and upgrading power plants will prolong plant life and increase efficiency, and the emergence of these dynamics in Asian countries opens the door to limitless opportunities for ABB, where a commitment to ‘evolution without obsolescence’ protects customer investments.

 

Ultrapure Water Discussion Group Updates in LinkedIn

 

11 November 16 Post:  Evoqua supplied CMS Energy needed with a water treatment system for the 155-megawatt Livingston Generating Station. The system had to withstand extreme cold and satisfy stringent environmental regulations.  It also needed to meet a peaking station's intermittent need for reliable demineralized water and NOx reduction water injection for the aeroderivative engines.

 

The 200 gpm system includes:

 

11 November 16 Post:  Replacement CEDI improves performance, lowers cost: A large power generating company in North America replaced a competitor's continuous electrodeionization (CEDI) system with one from Evoqua because of module leaking, scaling, slow delivery of replacement modules and short ten-month life. LX-MK modules are now operating with the following benefits:

 

11 November 16 Post:  Mobile DI system is the answer for East Coast CHP plant. An east coast power plant provides district heating. It originally treated raw water with its own deionization (DI) treatment plant to supply make-up boiler feedwater used to generate steam.  Because of safety concerns regarding handling of acid and caustic chemicals the company decided to convert the cation vessels to zeolite softeners. Shortly after, however, the city began to experience pipe failures caused by condensate corrosion from the additional carbonic acid being generated in the condensed steam.

 

The company decided to use mobile DI trailers from Evoqua Water Technologies to provide an immediate alternative to softened water. Four mobile DI trailers were installed to make boiler feed water for the site. An on-site service technician works with the energy company to ensure quality and quantity of water is provided daily. A two-year contract is resulting in successful delivery of high purity water at 2 MGD.

 

11 November 16 Post:  Xcel Energy Pueblo, CO, opts for offsite IE resin regeneration Xcel chose deep-bed ion exchange resin-based condensate polishers. This design typically requires a capital-intensive resin regeneration station, chemical storage/handling, waste neutralization/disposal and plant labor. Evoqua provided Xcel Energy with a service-based option to regenerate their condensate polisher resin off-site at a regionally located Evoqua's regeneration facility. Off-site regeneration services provide Xcel Energy with several cost benefits when compared to on-site regeneration, including preservation of capital by eliminating the need for a regeneration/neutralization system, elimination of fluctuating costs associated with chemical and waste handling, and optimization of manpower by keeping staff focused on Xcel’s core business.

 

11 November 16 Post:  A major power plant in California needed a new demineralizer, the plant needed to meet new pH discharge requirements and treat two different types of feed water. Reverse osmosis combined with CDI® systems from Evoqua Water Technologies was supplied. Some years later the company upgrade to CDI-LX systems for several reasons:

 

11 November 16 Post:  FPL has a long-term agreement for boiler feedwater. Evoqua Water Technologies and FPL entered a long-term agreement under which Evoqua provides boiler feed water to the plant on a cost-per-1,000-gallon basis.  FPL supplies the raw water, electricity and storage tank.  Evoqua supplies the equipment and operates and maintains the plant.  This ensures a continuous supply of boiler feed water that meets FPL's specifications of 2 megohm-cm quality water with 10 parts per billion (ppb) or less of silica.  Operation and maintenance costs are reduced, and there is no chemical handling or disposal required.

 

11 November 16 Post:  PSEG, Newark, NJ wanted to increase the water reuse capacity of the Bergen Station plant and design a system that would treat reclaimed water and make it pure enough to feed the station's boilers.  The installation of Evoqua Hydro-Clear filters resulted in a total reuse capacity of up to 10,000 GPM or 14.4 million GPD. By using recycled, treated wastewater for cooling tower makeup, in conjunction with closed loop cooling systems, the plant saves approximately 10 million gallons of city water per month. When Bergen Station's two combined-cycle generating units are operating, the mobile water treatment system saves an additional 400 GPM of city water.

 

CCR and ELG Discussion Group Updates in LinkedIn

 

11 November 16 Post:  A large Southern California power utility required assistance to drain a large cooling water intake system. The NPDES permit levels for this facility required treatment of nickel to 6.7 ppb along with low level organic compounds in a seawater background ionic chemistry. Evoqua supplied a system using SCU™ adsorptive media capable of reaching the desired treatment goal. Evoqua provided a complete, service-based treatment process that included pretreatment equipment, storage tanks, vessels containing media and activated carbon. As well, full on-site service was performed by Evoqua safety trained personnel on a 24/7 basis during project completion.

 

11 November 16 Post:  A Texas utility needed to remove copper from cooling water blowdown. The new permit requirements called for a substantially lower limit of 53 ppb copper. Evoqua supplied a system including activated carbon added prior to the ion exchange vessels to remove biocides and to protect the cation resin.  To increase the efficiency of the resin to remove copper, the pH of the blowdown water was reduced to <4; following the ion exchange vessels, the pH was increased to 6 for discharge.

 

11 November 16 Post:  A major power plant to be built on the west coast required water, wastewater and drinking water treatment systems - all in a single plant   Evoqua Water Technologies provided the process design, engineering, fabrication and supply of more than 10 integrated water treatment technologies, including:

 

           CDI-LX™ continuous electrodeionization systems

           Memtek® microfiltration systems

           HPD™ crystallizer

           J-Press® dewatering systems

           Chemical feed systems

 

11 November 16 Post:  Australia's Eraring Power Station, needed to treat secondary sewage from the nearby Dora Creek municipal wastewater plant for recycle as high-quality boiler feedwater Evoqua Water Technologies provided Eraring with a microfiltration and reverse osmosis (RO) system to treat secondary sewage and recycle the treated water to an existing deionizer.

 

Inlet Air Filtration

 

Should you select static or cleanable filters? Do you need high efficiency filters or are medium efficiency more cost effective? Do you need special coatings for coastal and marine environments? Are membranes better than laminates with nanofibers? Should you select synthetic or glass media?

 

5 December 16 Post:  There is lots of analysis already in GTRE Decisions. There is a child web on air treatment. It has a summary power point presentation just on air filter options. There are also recorded webinars on the subject. After you have had a chance to review this data, we invite you to ask questions and make comments. Also provide new case histories and white papers.

 

5 December 16 Post:  Advantages of coatings for Gas Turbine Air Filters.

One method to prevent fouling of gas turbines is to stop the small contaminants that reach the machine from sticking to the compressor blades. The use of hydrophobic and advanced fiber coated filters can stop the sticky contaminants from reaching the compressor and therefore prevent compressor fouling reports Steve Hiner of Clarcor in a Filtration News article.

 

There is a substantial difference between compressor performances when fitted with traditional F9 filters compared with enhanced F9 filters that have hydrophobic and advanced fiber coated media.

 

Both filters have approximately the same fractional efficiency when new. With traditional filters performance deteriorates between washes. The performance of the compressor shows little deterioration over time when media with advanced coatings were used to protect the system. The ideal filter solution provides high efficiency (fine fibers) as well as long service life (achieved using multi-layer composite media) that are highly pleatable to give performance and compactness in robustly (strong media) designed units. Operators require the filters to give predictable, reliable performance even with changing environmental conditions; meaning filters need to handle moisture effectively. Hydrophobic and advanced fiber coated filters have been shown to provide this performance in the harshest conditions such as coastal, offshore and desert installations as well as to prevent liquid corrosives from entering the turbine, which can cause permanent damage.

 

6 December 16 Post:  Moving from two to three stages has significantly increased system pressure drop but simultaneously reduced the quantity of dust reaching the turbine by approximately 98 percent, lowering the chance of engine damage – fouling, corrosion and erosion. To quantify this additional pressure drop, it is agreed within the power generation industry that an increase in pressure drop of 50 Pa causes a fall in efficiency of 0.1 percent. This is the conclusion in an article by Carlos Conti of Mann & Hummel Vokes.

 

Quantifying the benefit is a balance between reduced fouling and increased pressure drop. The increased pressure drop can be estimated to restrict performance by approximately 0.4 percent, while cutting fouling provides a 1.2 percent improvement in output (empirical average). Therefore, the overall result is a potential efficiency improvement of 0.8 percent. Other costs must also be considered in addition to the above. Investment is required in the retrofit of filter chambers, consisting of upgrades to the system housing (metal frames) to accommodate three stages of filters, for example. However, empirical research has shown that a 37 MW turbine operating continuously saved 2300 MWh in a year by changing from a two to a three-stage system incorporating EPA filters.

 

6 December 16 Post:  Vokes Macrogen GT Duo employs a hydrophobic media that provides effective water removal while in a study of 2 x 250 gas turbines in 2012 also showed particle filtration to G4 or M5 efficiencies. This means that separate coalescer and prefiltration stages are unnecessary and that the redundant filter phase can be removed. The F9 final filters downstream from the Macrogen GT Duo system ran for a greater number of hours and had a slightly lower pressure drop (105 against 110 Pascal) over the trial period. This result is due to the fact that the Macrogen has not only reduced the pressure drop but, at the same time, has increased the efficiency of prefiltration (from G4 to M5) better protecting the final filter.

 

Participate in the LinkedIn Discussion Groups

 

If you are a subscriber to 59D Gas Turbine Decisions, or are a utility employee you are eligible to participate in the following LinkedIn discussions. The discussions are a bridge between the webinars and the intelligence system which includes the database, so you can also send us case histories and white papers. The postings will be monitored to eliminate commercial messages which are not constructive. The service is free of charge to any power plant in the world, so, keep in mind that viewers might be from Asia or Africa. To join one of the discussion groups just click on the LinkedIn group and ask to join.

 

Power plant high performance pumps

Power plant ultrapure water

Power plant Lubrication

CO2 regulations and the power industry

HRSG Valve Decisions

Gas Turbine, Reciprocating Engine Inlet Air Treatment

 

For more information click on:  59D Gas Turbine and Reciprocating Engine Decisions

 

 

McIlvaine Company

Northfield, IL 60093-2743

Tel:  847-784-0012; Fax:  847-784-0061

E-mail:  editor@mcilvainecompany.com

Web site:  www.mcilvainecompany.com