Clyde Bergemann Wins Contract for Electrostatic Precipitator (ESP) Rebuild in
Michigan
The
Genesee Power Station in Flint, MI is a biomass-fired steam boiler which burns
wood waste, plus about 2% tire-derived fuel. The turbine/generator output is
approximately 35 MW. Genesee contracted the Clyde Bergemann Power Group Americas
(CBAM) for an Electrostatic Precipitator (ESP) rebuild. The scope includes
design, supply and installation of new internals comprised of new collecting
plates and RigitrodeTM electrodes for the first and third fields
of
the existing ESP.
The
Genesee ESP is a single chamber Joy Western rigid frame unit (circa 1995)
collecting fly ash from a biomass-fired boiler. It is equipped with three
mechanical fields, each with approximately 12 feet of treatment length and one
electrical section per field. Collecting plate panels are segmented (18”)
g-section with one Rigid Discharge Electrode (RDE) opposite each segment, 29
rows per field and lane spacing is 12”. In the inlet field the emitter tabs are
flared or “spread”.This Joy design uses vertical trusses (four perelectrical
field) to minimize sway. Cleaning on both frames is by pneumatic rapping system.
Fly ash is collected in a trough hopper with continuous evacuation via a drag
conveyor. The ESP is downstream of the ID fan.
Annual inspection information compiled over the years on the ESP determined it
had
reached its life cycle on some critical internal components. Issues included
missing Discharge Electrodes and Collecting Electrodes in the first and third
fields, material thinning
outlet ducting of the ESP, air in leaking causing ash accumulation and eroding
the ducting resulting in poor ESP performance.
While
the RFQ indicated the desire to replace all supports and framing for both the
collecting and discharge electrodes, CBAM assessed that such supports and
framing could be reused and proposed a more cost-effective approach for
upgrading the ESP. Recent inspections indicated the high voltage framing to be
in satisfactory condition and the field arrangement revealed a reduction in
collecting area would be required to accommodate different collecting system
supports.
CBAM
proposed a retrofit that utilized a shop assembled collecting plate design with
the same hanger mechanism currently in use in the ESP design. For the high
voltage discharge electrodes, CBAM Rigitrodes were used, however, the pins were
turned 90 degrees from their normal orientation to allow attachment to the high
voltage framing in a method similar to that currently in use in the Joy ESP.
This retrofit includes reusing all rapper hardware, also the existing rapper
anvil beams and rapper trains.
After
inspection and working with the customer, CBAM secured the order for rebuilding
the ESP. The customer was confident with CBAM after cooperating over two plus
years providing annual inspections and a cost-effective solution.